Abdool Raman Abdool GS, Port Louis - Ongoing
 
Project:    Reconstruction of a 3-stream school to be carried out in 2 phases.
 
Phase IDemolition of old classroom block & Construction of 3-Storey Classroom block to house a pre-primary unit at the Ground floor , a Computer Block at 2nd floor (the levels below would be void), Kindergarten with playing equipment. Works also comprise electrical works and New Entrance Gate
 
Start Date                                        :        07 January 2015
Expected Completion Date         :        September 2016
 
Phase II
 
Phase II will start after the completion of Phase I.
 
Phase II ADemolition of Single Storey Building and construction of a new classroom Block Ground plus two (G + 2) + Toilet Block
Phase II B: Demolition of Existing Toilet Block & Construction of Administrative Block, Classrooms (G+2) & Staircase
Phase II CDemolition of remaining blocks & Construction of playfield
Status:​ Drawings and Bidding documents under preparation​